FlameOut has been involved in the supervision of the installation of a new 90m flare stack with 4 levels of guy wires in Qatar for John Zink Hamworthy Combustion.
The John Zink project was undertaken successfully in record time and the complete site installation only took 10 days from start to finish!
The flare stack was also fabricated in record time (4 weeks) in the U.A.E. under John Zink’s control and was shipped to site in sections: Knockout Drum, Riser Sections, Molecular Seal, 2 x Flare Tips, etc.
Key to the success of the project was FlameOut’s sequenced installation and tensioning of the 4 levels of guy wire assemblies and overall supervision of the Main Contractor’s activities.